Institute Site Activity 6/16/23
We are moving to monthly updates from this date forward, unless there is a specific site related activity of significance which then you will be notified.
Overview for the next month is as follows:
- Inn: Continue exterior framing/panels on the third floor of the Inn. A crane will be on site on Monday to begin erecting panels and walls on the third floor. Roof trusses to follow in the next three to four weeks.
- Mechanical rough-in of piping for first and second interior floors of the Inn has also started and will continue over the next month.
- Institute: continue framing exterior walls and installing exterior sheathing as well as framing for curtain wall. Masonry contractor is expected to start on or about 6/20/23 and will be installing vapor barrier with brick installation to follow in the first week of July.
- Roofing has begun on the Institute penthouse roof and will continue throughout the month.
- Site utilities continue to be installed for water, sewer and electric throughout the site.