Institute Site Activity 12/13–12/16/22

[SLIDESHOW] All footings and lower walls have been placed except for elevators 3 and 4 which will be poured next week. Only 7 Geothermal wells remain, and the horizontal crew will be on site the week of 19th to begin the next phase. We plan to submit under slab coordination early next week and are working […]

Institute Site Activity 12/05–12/16/22

Continuation of forming, reinforcing and pouring concrete piers and stem wallsContinuation of geothermal well drilling on both the south and north end of siteContinuation of accompanying site activities; excavation and backfillingInstall brick at curtain wall mock up on siteWe will be offering hard hat tours of the site on 12/7/22 and 12/8/22 to view the project […]