Institute Site Activity 12/13–12/16/22
[SLIDESHOW] All footings and lower walls have been placed except for elevators 3 and 4 which will be poured next week. Only 7 Geothermal wells remain, and the horizontal crew will be on site the week of 19th to begin the next phase. We plan to submit under slab coordination early next week and are working towards some great milestones as we close in on the end of the year.