Institute Site Activity 2/21/23

Due to expected rain in the afternoon tomorrow, we are going to hold off on the slab pour for the Inn. This work was scheduled for Tuesday 2/21/23. We are now hoping to complete this work on Wednesday, but that will be dependent on the weather. We will keep you updated.

Institute Site Activity 2/17/23

Concrete Slab at the Inn: We are preparing the slab on grade for a concrete pour at the Inn which will take place on Tuesday 2/21/23. Due to today’s rain we will be required to work this Saturday 2/18/23 from the hours of 7:30 to 3:30. There will be no heavy equipment running. The contractor will be […]

Institute Site Activity 2/03/23

Beginning on Monday 2/6/23 the steel for the Institute and connector will arrive on site. In addition a crane will be on site to off load the steel and begin erecting the building. The steel erection process is expected to take 2 to 3 weeks and is weather dependent. The next milestone is to start […]